Bathroom Project Calendar

Week 1 (May 30)
Demolition!
Week 2 (June 6)
Prep work, rough plumbing. Working toilet installed!
Week 3 (June 13)
Rough plumbing, rough electrical
Week 4 (June 20)
Rough framing, insulation
Week 5 (June 27)
Install board and plaster
Week 6 (July 4)
Cabinets and trim installed
Week 7 (July 11)
Tile walls and floors installed
Week 8 (July 18)
Tiling cont., finish electrical work
Week 9 (July 25)
Final plumbing and building inspection, our fabulous new bathrooms are finished!