| Week 1 (May 30) |
Demolition! |
| Week 2 (June 6) |
Prep work, rough plumbing. Working toilet installed! |
| Week 3 (June 13) |
Rough plumbing, rough electrical |
| Week 4 (June 20) |
Rough framing, insulation |
| Week 5 (June 27) |
Install board and plaster |
| Week 6 (July 4) |
Cabinets and trim installed |
| Week 7 (July 11) |
Tile walls and floors installed |
| Week 8 (July 18) |
Tiling cont., finish electrical work |
| Week 9 (July 25) |
Final plumbing and building inspection, our fabulous new bathrooms are finished! |